Home Building

We exceed the standard in home building.

Quality homes that last a life time are the kinds of homes you will get with Cahoon Construction. 

Cahoon's Construction Process  

Pre-Construction and Contract Signing

Your home plan is reviewed by Cahoon Construction, initially for plan and site design. Once approved, we then sign a contract for building. After the contract is signed, our purchasing team then buys the materials to build your home.

Stage 1

Your home site is cleared and prepped for pouring the foundation. Forms are set and plumbing rough is completed. Inspection by city officials, engineer, and Grand Homes Quality Control Team.

Stage 2

Foundation is now poured.

Framework is completed.

Stage 3

Rafters are installed to complete the frame.

 

Stage 4

Install windows and exterior doors, roofing and weather proof house wrapping. Now your home is safe from out door elements.  Then we do decking, cornice, siding are installed. Mechanical roughs are completed including plumbing “top-out” and HVAC rough.

Vents and skylights if applicable.

Stage 5

Additional mechanical roughs are installed which include electric rough, entertainment rough and security rough. Gas lines are installed. Now, City Inspectors and the Cahoon Quality Control Team do framing and mechanical inspections.

Stage 6

Brickwork begins and insulation is installed.

 

Pre-sheetrock Inspection: A pre-sheetrock inspection with you, Cahoon Construction now occurs. The inspection and review will cover the entire structure, including placement of electrical plugs and switches, cable television outlets, telephone outlets, color selections, and any changes you requested to the plan. The pre-sheetrock inspection is critical to insure that the timely completion of your home is not delayed due to incorrect installation or misinterpretation of your changes.

After pre-sheetrock approval is granted, sheetrock installation begins and is followed by the taping, bedding, and texturing of the walls. The flatwork, which includes driveways, sidewalks, and patios, is installed.

Stage 7

At this stage, exterior painting is done. Finish carpentry that includes stair trim out, cabinets, countertops, trim, doors, and mantles is completed. Baths and backsplash are tiled.

Stage 8

Wall out and trim prep inspection is completed. Interior walls and trim are painted. Vanities are now installed. HVAC and plumbing trim out is done.

Stage 9

Electrical, entertainment and security trim out is completed. Wallpaper is now installed as well as mirrors and shower doors. Back yard fence is installed and final survey is taken.

Stage 10

The floors are laid and fireplaces are tiled. Trim hardware and locks are installed. Landscaping and irrigation are completed. Any touch-up work to the paint is done and there is a pre-carpet inspection. Once approval is given, the carpet is installed. Final clean of the interior and exterior is done and appliances are checked for any defects.

Stage 11

Gas and electric meters are installed. A final building inspection is completed and home is now ready for your homeowner orientation and walk through with your builder. At this point, any item that you believe needs our attention can be listed on your Homeowner Orientation Form. This is an important step because minor cosmetic repairs are not covered by the warranty after closing. 

Completed Home

Once we have met all your requirements, you, the homeowner, will enjoy your first walkthrough of your completed home. After the tour is done and you have no more question or concerns, a Cahoon Construction Quality feedback form is completed and the contract is fullfilled.